The Mundra Thermal Power Project was conceived to provide power for the captive consumption of  APSEZ  in  Mundra. Thereafter the vision and the capabilities of the promoters has made Mundra Power project the largest single location Coal based Thermal Power Station in India and one of the top five in the World. All the nine units of Mundra power plant have been commissioned one after the another in shortest possible time of 33 months.

Mundra, Gujarat

4620 MW (5 X 660 MW + 4 X 330 MW)

Largest single location private coal based power plant in the world

Adani Power created history by synchronising the first super-critical technology based 660MW generating unit at Mundra. This is not only the first super-critical generating unit in the country but also the fastest project implementation ever by any power developer in the country with synchronisation within 36 months from the inception,.

The Phase III of the Mundra Project, which is based on supercritical technology, has received ‘Clean Development Mechanism (CDM) Project’ certification from United Nations Framework Convention on Climate Change (UNFCCC). This is the world’s first thermal project based on supercritical technology to get registered as CDM Project under UNFCCC.

 (Click here for the copy of Environmental Compliance)
 

Mundra,

Tiroda, Maharashtra

3300 MW (5 X 660 MW)

With its total capacity of 3300 MW, Tiroda comprises of 5x660 MW units. All units at this location are of Supercritical Technology, driving efficiency in coal based power generation.
Tiroda uses latest technology for environment management and has been registered under CDM by UNFCCC.

(Click here for the copy of Environmental Compliance)




 

Tiroda,

Kawai, Rajasthan

1320 MW (2 X 660 MW)

Kawai has a total installed capacity of 1320 MW and has the capability to expand in future. Kawai comprises of 2x660 MW units.
For immediate connectivity, Kawai has a 1500m long air strip and is using state of the art technology for environment management.

(Click here for the copy of Environmental Compliance)


 

Kawai,

Udupi, Karnataka

1200 MW

Udupi Power Corporation Limited is a 2 X 600 MW imported coal based power project in the Udupi District of Karnataka.

Situated in the western coastal region of India, the plant is situated in the village of Yellur, between Mangalore and Udupi.

UPCL is the first independent power project (IPP) using 100% imported coal as fuel in the country and was awarded the Gold Shield award for early completion of Thermal power project Unit-1 from Ministry of power, Government of India in FY 2010-11 and also the prestigious Golden Peacock Environment Management Award in FY 2014-15.

The Udupi Power Project supplies 90% of the power it generates to the State of Karnataka and 10% to the State of Punjab.

Udupi,

Other projects

Three of our projects with additional capacity of 7260 MW are in different stages of regulatory and statutory clearances. Other projects include 3300 MW project in Bhadreshwar and 2640 MW project in Dahej both in Gujarat and a 1320 MW project in Chhindwara.

Pench Thermal Power Project (Upcoming)


Location :  Chhindwara, District Chhindwara, Madhya Pradesh, India

Capacity  : 1320 MW

The Pench Thermal Power Project of 1320 MW is being set up by Adani Pench Power Limited, a subsidiary of Adani Power Limited. In line with our commitment to the environment all the units are based on supercritical technology. The project is in advanced stage of development and the project is planned to be commissioned in the second year of the XIIth Five Year Plan. Environmental Clearance was granted on 16.10.2012 for the Project (Click here for the copy of Environmental Clearance). 

(Click here for the copy of Environmental Compliance)

 

Dahej Thermal Power Project (Upcoming)
Location :  GIDC-Dahej, District Bharuch, Gujarat, India
Capacity  : 2640 MW
The Dahej Thermal Power Project of 2640 MW is being set up by Adani Power DahejLimited, a subsidiary of Adani Enterprises Limited. All the units are based on supercritical technology. The project is in advanced stage of development and the project is planned to be commissioned by the end of the XIIth Five Year Plan. Environmental Clearance was granted on 26.10.2011 for the Project.

(Click here for the copy of Environmental Compliance).
 

Other